Getting knowledge of the Broadcom 250-563 exam structure and question format is vital in preparing for the Symantec Rally Technical Specialist certification exam. Our Broadcom Rally Technical Specialist sample questions offer you information regarding the question types and level of difficulty you will face in the real exam. The benefit of using these Broadcom 250-563 sample questions is that you will get to check your preparation level or enhance your knowledge by learning the unknown questions. You will also get a clear idea of the exam environment and exam pattern you will face in the actual exam with the Symantec Rally Technical Specialist Sample Practice Test. Therefore, solve the Broadcom Rally Technical Specialist sample questions to stay one step forward in grabbing the Broadcom Rally Technical Specialist credential.
These Broadcom 250-563 sample questions are simple and basic questions similar to the actual Broadcom Rally Technical Specialist questions. If you want to evaluate your preparation level, we suggest taking our Symantec Rally Technical Specialist Premium Practice Test. You might face difficulties while solving the real-exam-like questions. But, you can work hard and build your confidence on the syllabus topics through unlimited practice attempts.
Broadcom 250-563 Sample Questions:
01. The user sign-on authentication features in Rally allow for which of the following options.
(Select all that apply)
a) Rally authentication
b) Single Sign On
c) Tasktop Hub
d) JIRA Integrator
e) OKTA
02. When closing an iteration in Rally, change its state to:
a) Planning
b) Committed
c) Accepted
d) Finished
e) Complete
03. To schedule a work item into an iteration on the Team Planning page, you must have at least:
a) Program Administrator permissions
b) Project Editor permissions
c) Project Viewer permissions
d) Workspace Administrator permissions
04. When does the Release Planning event happen?
a) Only at the beginning of the release cycle
b) Only at the end of the release cycle
c) At the beginning and end of the release cycle
d) At the beginning of the release cycle, and then repeats for each release cycle in the future
05. What should you use to indicate if a user story is dependent upon the completion of another user story?
a) Risks
b) Dependencies
c) Tasks
d) Blocked Reason
06. When you initially select a team on the Capacity Planning page, which of the following statements about the capacity field are TRUE?
a) It defaults to 100
b) It is in hours
c) It is in Points
d) It is blank
e) It is set to the same number that is in the Release Planned Velocity within Timeboxes
07. Which actions can you perform using the Rally Add-in for Excel, also known as the Excel plugin?
a) Export data from Rally
b) Update data in Rally
c) Delete data in Rally
d) Import data into Rally
08. When you set your profile in Rally, which actions can you perform?
(Select all that apply)
a) Upload a picture
b) Specify a display name
c) Enable email notifications
d) Choose a default start page
e) Connect to other social media sites
09. What is the maximum number of flow states that you can have?
a) Twelve
b) Five
c) Eight
d) Ten
10. When you use a portfolio Kanban, what can you more easily view?
(Choose three answers)
a) Which portfolio items have added scope
b) Which portfolio items have started
c) Which portfolio items have not started
d) How many portfolio items are in each state
Answers:
Question: 01 Answer: a, b |
Question: 02 Answer: c |
Question: 03 Answer: b |
Question: 04 Answer: d |
Question: 05 Answer: b |
Question: 06 Answer: a, c |
Question: 07 Answer: a, d |
Question: 08 Answer: a, b, c |
Question: 09 Answer: a |
Question: 10 Answer: b, c, d |
Note: For any error in Symantec Rally Technical Specialist (250-563) certification exam sample questions, please update us by writing an email on feedback@certfun.com.